Mounting & civil worksGround-mounted plants

Ground-Mount Piles and Embedded Foundations

Transfers array weight, wind uplift and overturning forces into the ground. Selection requires both geotechnical findings and structural calculations.

Features & function

  • Options include driven and screw piles
  • Capacity depends on soil layers and groundwater
  • Corrosion resistance affects plant service life

What should you verify when selecting?

  • Obtain geotechnical and corrosivity findings
  • Plan trial piles and pull-out testing
  • Check pile positions against buried utilities
EmbedmentDetermined by geotechnical and uplift design
MaterialSelected for the corrosion environment
AcceptanceFollow the design testing and sampling plan

Installation procedure

This guide explains installation logic and checkpoints. Dimensions, torque, protection settings, test values and operating sequences must follow approved project documents and the purchased model's manual. Electrical work is for qualified personnel.
1

Setting out

Use survey control points and identify underground services.

2

Trial verification

Construction and testing specialists validate the installation method and bearing capacity.

3

Production installation

Record verticality, elevations and treatment of abnormal piles.

Operation & maintenance guidance

Correct use

  • Manage assets using as-built pile coordinates
  • Have structural specialists review settlement
  • Keep maintenance vehicles clear of posts

During operation

  • Inspect erosion and settlement
  • Check corrosion near ground level
  • Keep drainage channels clear

Common misuse

  • Copying pile lengths from another site
  • Expanding on weak soils without testing