Real photographyWhat this stage delivers
Deliverables
- Survey and setting-out records
- Foundation and anchorage inspection records
- Roof waterproofing detail acceptance
- As-built underground service and earthing drawings
- Road and drainage completion records
Common oversights
- Loading foundations before release conditions are met
- Focusing on sealant while ignoring the structural connection
- Closing trenches and buried services without position records
Which equipment is used at this stage?
These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.
Materials and equipment in this stage
- Reinforced-concrete foundations
- Screw piles or precast piles
- Embedded anchor bolts
- Roof waterproofing materials
- Cable trenches and conduits
- Earthing conductors
- Equipment bases and fencing
Work steps & checkpoints
Excavation, lifting, work at height and roof hot work require appropriate work organisation and site authorisation.
Do not concentrate modules, ballast or concrete materials on a roof whose capacity has not been verified.
Set up work boundaries and survey references
Define construction, storage and pedestrian zones, then verify survey benchmarks and underground services. Confirm service locations and permits before excavation. For roofs, arrange edge protection, distributed material storage and temporary drainage. Construction planning must allow the existing factory or home to continue operating safely.
Build and test foundation samples
Construct trial foundations or representative samples according to the ground investigation, loading and approved method. Verify that the construction equipment can meet the design. For piles, check position, verticality and field-test results; for concrete, check reinforcement, anchors and curing. Experience on another plot cannot replace project-specific testing and acceptance.
Complete roof attachments and waterproofing
Attach to verified load-bearing parts of the roof using details compatible with its waterproofing system. Install penetrations, clamps and seals to the approved drawings, and first correct existing corrosion, damage or leaks. Preserve concealed-work photographs and water-test or inspection records; surface sealant cannot conceal an unresolved structural defect.
Build electrical bases and cable routes
Prepare inverter, transformer, switchboard and storage bases for actual equipment weights, lifting directions and maintenance access. Design trenches and conduits for drainage, bends, inspection and penetration sealing, with power and communications separated as specified. Verify embedded parts and interface dimensions against final supplier drawings.
Complete drainage and site restoration
Review roof outlets, surface runoff and road drainage as one system. Prevent foundations from obstructing flow or trenches from becoming water channels. Ground projects also need slope, erosion and vegetation planning; carports need vehicle-clearance and discharge checks. Remove debris so later work cannot damage drainage facilities.
Accept concealed work before handover
Before backfilling, closing works or erecting mounting structures, record the actual locations of foundations, earthing, conduits and waterproofing details. Designers, contractors and inspectors should confirm deviations and corrections as the project requires. Provide usable as-built dimensions and allow loading or the next activity only after the specified conditions are met.
Stage acceptance checklist
For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.
0 / 4 checked
Original technical sources
- DOE | Installation, structural and commissioning considerationswww.energy.gov
- China National Energy Administration | PV power station development and construction managementzfxxgk.nea.gov.cn
- K2 Systems | SingleRail systemk2-systems.com
Sources provide general background or model-specific information. Foreign standards do not replace local requirements; obtain the latest manuals for the actual equipment before purchasing or construction.