What this stage delivers

Commercial & industrial roofsGround-mounted plantsResidential

Deliverables

  • DC string and circuit schedule
  • Cable and terminal assembly records
  • Polarity and electrical test records
  • DC protection and surge-protection schedule
  • As-built cable-route drawings

Common oversights

  • Treating “MC4-like” as evidence of connector compatibility
  • Disconnecting DC connectors under load
  • Checking continuity without recording polarity and insulation
  • Applying an insulation test without first isolating sensitive equipment

Which equipment is used at this stage?

These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.

Materials and equipment in this stage
  • PV DC cables
  • Matching-series PV connectors
  • Manufacturer-approved crimp tools
  • DC combiner boxes
  • PV fuses
  • DC isolating switches
  • DC surge-protection devices
  • Cable clips and trays

Work steps & checkpoints

Never mate or disconnect DC connectors under load. Pulling faster does not remove the arc hazard.

Only trained, authorised personnel may isolate circuits or perform electrical tests, following equipment instructions and project procedures.

1

Identify circuits and plan isolation

Match each string, input and isolation point to the drawings and identify voltage that may come from modules, storage or other sources. Before work, the electrical lead must establish the work boundary and isolation verification. Use weather-resistant labels that trace equipment back to the array, not just colour coding or memory.

Checkpoint · String labels match at both ends, and isolation points and possible supplies are identified.
2

Install PV cables to the design

Use cables suitable for system voltage, temperature and environment. Control routes, support and bending conditions according to drawings. Avoid sharp edges, standing water, heat sources and moving parts, and protect tray and wall crossings. Follow the designed positive and negative routes rather than creating unnecessary loops or confusing crossings.

Checkpoint · Cable type, route, support and mechanical protection match the design.
3

Assemble DC connectors under controlled conditions

Select cables, contacts, seals and approved tools for the exact connector brand and series. Trained personnel should strip, crimp and assemble them, checking conductor condition, seal fit and locking, with inspections required by the quality plan. Do not cross-mate different manufacturers’ connectors based on similar appearance or a generic compatibility claim.

Checkpoint · Contacts, cable diameter, tools and assembly instructions agree, with inspection records retained.
4

Install combining and DC protection

Confirm the design requirements for combiner boxes, string fuses and external isolation. Verify DC ratings, polarity, environmental protection and earthing. Match surge protection to system topology and voltage, and seal enclosure entries. An AC breaker is not suitable for DC merely because its current marking is the same.

Checkpoint · Protection, fuse arrangements and switch ratings satisfy the design conditions.
5

Check polarity and insulation

Qualified electrical personnel should follow an approved test plan using instruments suitable for system voltage and measurement category to verify circuit identity, polarity, insulation and required electrical quantities. First confirm test restrictions for inverters, surge devices and electronics. This overview does not specify a universal test voltage or live-connection procedure.

Checkpoint · Tests, conditions, instruments and results are recorded; abnormal circuits remain unreleased.
6

Inspect completed connections and hand over

Check that mated connectors are fully engaged, locked, supported and protected against water, and address unused ports and exposed terminals. Confirm cables are not trapped under modules or cut by mounting edges. Map combiner boxes and inverter inputs into monitoring, and retain repaired-connection records together with retest results.

Checkpoint · Every string has a traceable inspection status, and unused ports are correctly sealed.

Stage acceptance checklist

For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.