Real photographyWhat this stage delivers
Deliverables
- Site and module-layout drawings
- Structural and foundation calculations
- Electrical single-line and string diagrams
- Protection, earthing and lightning-protection design
- Energy-yield and loss-breakdown report
- Equipment and materials schedule
Common oversights
- Treating one DC/AC ratio as universal
- Changing to higher-current modules without checking inverter inputs
- Overlooking maintenance routes and equipment replacement space
Which equipment is used at this stage?
These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.
Materials and equipment in this stage
- PV modules
- String inverter
- Fixed or tracking mounting system
- DC cables and connectors
- Distribution and protection equipment
- Step-up transformer
- Design and simulation software
Work steps & checkpoints
Engineering calculations and final design belong to professionals with the qualifications and capability required for the project.
Select the system architecture
Compare string, central and module-level architectures against project scale, grid conditions, shading and service access. Define DC, AC and metering boundaries first. If storage is included, identify AC or DC coupling. Put future expansion and backup requirements into the drawings rather than adding equipment as an afterthought.
Optimise layout and structure
Arrange the array around orientation, spacing, maintenance and fire-access routes, and shading calculations. Check foundations and mounting against local design loads. Bifacial modules also require rear-shading, ground-clearance and reflectance analysis. Balance denser installation against shading, construction constraints and future maintenance costs.
Check string voltage and current
Use the actual module temperature coefficients and design low and high temperatures to check string open-circuit and operating voltages. Then verify the inverter’s input maximum, MPPT range and input-current limits. Bifacial gain and parallel strings can increase current. Do not combine differing orientations or shading on one tracking input without analysis.
Coordinate cables and protection
Select cables for current capacity, voltage drop, installation temperature, grouping, UV exposure and environment. Coordinate protection with voltage, fault current and equipment withstand capability. Design lightning protection, surge protection, earthing and bonding together. Verify DC and AC device suitability separately rather than treating them as interchangeable.
Review annual generation and losses
Model energy using local resources and equipment data, separating temperature, shading, soiling, mismatch, wiring, inverter and curtailment effects. Evaluate clipping and low-irradiance gains when changing the DC/AC ratio, not just nominal efficiency. Do not deduct a loss again as an extra percentage if the model already calculates it explicitly.
Hold an interdisciplinary design review
Have structural, electrical, fire-safety, construction and maintenance teams review the drawings together. Check lifting routes, replacement space, isolation labels and pedestrian access. Reconcile utility requirements and manufacturer manuals into an approved construction version. Any equipment substitution requires renewed compatibility checks, not approval based only on equal rated power.
Stage acceptance checklist
For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.
0 / 5 checked
Original technical sources
- DOE | Solar photovoltaic system design basicswww.energy.gov
- NLR PVWatts | System loss modelpvwatts.nlr.gov
- NLR SAM | Detailed photovoltaic modelssam.nlr.gov
- SMA | SUNNY TRIPOWER CORE1 operating manualmanuals.sma.de
Sources provide general background or model-specific information. Foreign standards do not replace local requirements; obtain the latest manuals for the actual equipment before purchasing or construction.