What this stage delivers

Commercial & industrial roofsGround-mounted plantsResidential

Deliverables

  • Module serial-number location map
  • Visual and sample-inspection records
  • Clamping-position and tightening records
  • String and polarity labels
  • Quarantined-module register

Common oversights

  • Checking watts but ignoring current and dimensions
  • Standing on modules or lifting them by cables
  • Using arbitrary clamp positions or drilling new frame holes
  • Assuming modules become electrically dead when AC is switched off

Which equipment is used at this stage?

These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.

Materials and equipment in this stage
  • Monofacial PV modules
  • Bifacial glass-glass modules
  • Compatible mid and end clamps
  • Handling suction cups and lifting equipment
  • Protective insulating caps
  • Weather-resistant labels
  • Module testing equipment

Work steps & checkpoints

Modules can produce DC electricity in light. Switching off the inverter does not stop the modules generating.

Qualified personnel must assess and isolate broken glass or exposed conductors. Do not touch them or attempt to keep them operating with adhesive repairs.

1

Confirm module identity and installation limits

Check nameplates, serial numbers, models and datasheets, confirming dimensions, weight, current and system voltage against the design. Understand the differences between glass-backsheet, glass-glass, bifacial and cell technologies. Review permitted orientation, clamp zones and loading conditions. Similar product names do not mean identical installation limits.

Checkpoint · Actual modules match the string design and mounting hardware.
2

Unpack and handle correctly

Follow the packaging instructions, unpack in a suitable location and keep modules stable. Use enough people and appropriate tools for their size and weight. Protect corners, glass and backsheets; never stand on modules, pull their cables or carry them by junction boxes. Stop handling when wind or panel size makes control unsafe.

Checkpoint · Record packaging, visual condition and handling damage; quarantine abnormal items.
3

Install modules to the location plan

Follow the module map and link each installed serial number to its position. Maintain the required spacing, drainage and maintenance access. Do not bend a module to make it fit the frame, or obstruct frame drainage holes and ventilation. For bifacial modules, also check avoidable shading from rear structures, cables and areas around junction boxes.

Checkpoint · Layout, spacing and identification are correct, with clear rear and drainage spaces.
4

Secure modules to their instructions

Place clamps only on manufacturer-approved areas and surfaces, compatible with frame height, mounting system and project loads. Use and record the specified tightening method. Do not introduce unapproved holes or clamping arrangements. Insufficient tightening can allow movement, while excessive tightening can damage the module.

Checkpoint · Clamp zones, tightening parameters and hardware combinations have documented support.
5

Route factory cables and protect connectors

Place module leads in the approved support route with suitable movement allowance, avoiding tension, sharp bends and persistent water exposure. Protect unmated connectors from moisture and dirt as instructed. Verify brand, series and polarity before connection. Qualified personnel must make electrical connections under the required isolation conditions.

Checkpoint · Connectors are supported and unstressed; terminal protection and string labels are complete.
6

Inspect the installation and hand it over

Inspect glass, frames, junction boxes, clamps, cables and earthing connections. Carry out electroluminescence or other testing where the quality plan requires it. Link defects to serial numbers and inspect again after repair or replacement. Keep the location map so future fault finding does not require resurveying the entire array.

Checkpoint · Module quality and mechanical acceptance are complete, and location data can be exported.

Stage acceptance checklist

For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.