What this stage delivers

Commercial & industrial roofsGround-mounted plantsResidential

Deliverables

  • Project objectives and requirements
  • Site ownership and use-agreement checklist
  • Electricity consumption and load data
  • Preliminary grid-connection consultation records
  • Financial model and risk register

Common oversights

  • Sizing only from available area and ignoring energy use or grid access
  • Presenting forecast generation or payback as guaranteed
  • Failing to plan an exit when roof lease and equipment life do not match

Which equipment is used at this stage?

These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.

Materials and equipment in this stage
  • Energy data logger
  • Smart electricity meter
  • Load recorder
  • PV energy-modelling software
  • Project document management system
  • Geographic base map

Work steps & checkpoints

Budget for structural assessment, fire-safety design and qualified electrical installation from the start; these are not optional savings.

1

Define demand and project objectives

Turn the objectives into verifiable requirements: reducing electricity purchases, selling energy, improving supply resilience or meeting corporate renewable-energy goals. Gather weekday, weekend and seasonal load profiles. Define usable roof areas, acceptable shutdown windows and funding constraints separately, rather than combining several different objectives into a single capacity target.

Checkpoint · Objectives, load-data time resolution, asset owner and budget responsibility are clear.
2

Document site ownership and access rights

Collect land or building ownership records, lease terms, roof repair history and information on existing equipment. Confirm who approves construction, who pays for leak repairs and what happens to the plant when ownership changes. Assess the lease, remaining roof life and equipment service life together; resolve contractual gaps before procurement.

Checkpoint · Document permitted areas, duration, roof-repair responsibility and exit arrangements.
3

Check grid access early

Consult the local utility and relevant authorities about the project classification, connection point, available capacity, metering and registration requirements. Describe self-consumption, exported energy and export limits separately. Include proposed storage, backup sources and capacity changes in the consultation; another region’s process is not permission for this project.

Checkpoint · Grid conditions have a source, date and action list; outstanding approvals are identified.
4

Estimate capacity and generation

Develop several capacity options from usable site area and an initial layout. Include local weather, shading, temperature and system-loss assumptions. Preliminary tools provide conditional estimates: do not multiply peak power by every hour in a year. Allow the survey to refine the inputs and record the weather-data source.

Checkpoint · Capacity, orientation, losses and weather assumptions are traceable for every option.
5

Calculate revenue by energy destination

Align forecast generation with the load profile and separate self-consumed energy, exports, curtailment and storage losses. Include grid connection, roof reinforcement, insurance, maintenance, financing, replacements and decommissioning. Compare scenarios for electricity prices and changing demand, rather than promising a particular payback period.

Checkpoint · No unit of energy is counted twice, and costs cover the full project life cycle.
6

Set proceed-or-pause decision gates

Bring the owner, designers, contractors and maintenance team together to review structural, fire-safety, site, grid and financial conditions. Treat unacceptable risks as hold points and assign each unresolved item to a named person. Move into detailed survey and design only once the critical prerequisites are established.

Checkpoint · Record the decision, responsibilities, outstanding conditions and next-stage budget.

Stage acceptance checklist

For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.