Real photographyWhat this stage delivers
Deliverables
- Project objectives and requirements
- Site ownership and use-agreement checklist
- Electricity consumption and load data
- Preliminary grid-connection consultation records
- Financial model and risk register
Common oversights
- Sizing only from available area and ignoring energy use or grid access
- Presenting forecast generation or payback as guaranteed
- Failing to plan an exit when roof lease and equipment life do not match
Which equipment is used at this stage?
These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.
Materials and equipment in this stage
- Energy data logger
- Smart electricity meter
- Load recorder
- PV energy-modelling software
- Project document management system
- Geographic base map
Work steps & checkpoints
Budget for structural assessment, fire-safety design and qualified electrical installation from the start; these are not optional savings.
Define demand and project objectives
Turn the objectives into verifiable requirements: reducing electricity purchases, selling energy, improving supply resilience or meeting corporate renewable-energy goals. Gather weekday, weekend and seasonal load profiles. Define usable roof areas, acceptable shutdown windows and funding constraints separately, rather than combining several different objectives into a single capacity target.
Document site ownership and access rights
Collect land or building ownership records, lease terms, roof repair history and information on existing equipment. Confirm who approves construction, who pays for leak repairs and what happens to the plant when ownership changes. Assess the lease, remaining roof life and equipment service life together; resolve contractual gaps before procurement.
Check grid access early
Consult the local utility and relevant authorities about the project classification, connection point, available capacity, metering and registration requirements. Describe self-consumption, exported energy and export limits separately. Include proposed storage, backup sources and capacity changes in the consultation; another region’s process is not permission for this project.
Estimate capacity and generation
Develop several capacity options from usable site area and an initial layout. Include local weather, shading, temperature and system-loss assumptions. Preliminary tools provide conditional estimates: do not multiply peak power by every hour in a year. Allow the survey to refine the inputs and record the weather-data source.
Calculate revenue by energy destination
Align forecast generation with the load profile and separate self-consumed energy, exports, curtailment and storage losses. Include grid connection, roof reinforcement, insurance, maintenance, financing, replacements and decommissioning. Compare scenarios for electricity prices and changing demand, rather than promising a particular payback period.
Set proceed-or-pause decision gates
Bring the owner, designers, contractors and maintenance team together to review structural, fire-safety, site, grid and financial conditions. Treat unacceptable risks as hold points and assign each unresolved item to a named person. Move into detailed survey and design only once the critical prerequisites are established.
Stage acceptance checklist
For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.
0 / 4 checked
Original technical sources
- US EPA | On-site project development processwww.epa.gov
- China National Energy Administration | Distributed PV management Q&A, 2025www.nea.gov.cn
- NLR PVWatts | Yield estimation inputs and limitationspvwatts.nlr.gov
Sources provide general background or model-specific information. Foreign standards do not replace local requirements; obtain the latest manuals for the actual equipment before purchasing or construction.