What this stage delivers

Commercial & industrial roofsGround-mounted plantsResidential

Deliverables

  • Survey drawings and photographic records
  • Shading and solar-access assessment
  • Structural or geotechnical investigation records
  • Connection-point and distribution-equipment records
  • Environmental and transport constraints

Common oversights

  • Using drone imagery instead of a structural investigation
  • Missing skylights, fragile rooflights or fire and maintenance routes
  • Checking shading and ponding only on a sunny day at noon

Which equipment is used at this stage?

These entries relate to this stage. Open each for features, selection criteria, installation and operating guidance.

Materials and equipment in this stage
  • Total station and positioning equipment
  • Laser distance meter
  • Irradiance meter
  • Survey drone
  • Roof inspection tools
  • Power-quality analyser
  • Weather datasets

Work steps & checkpoints

Before a roof survey, confirm load capacity, edge protection and rescue arrangements. Rooflights are generally not walking surfaces.

Do not open distribution cabinets or make live measurements without authorisation.

1

Verify drawings against actual boundaries

Check building or plot boundaries using measured dimensions. Locate parapets, skylights, flues, fire-safety equipment, access hatches and existing services. Drone imagery adds an elevated view but does not replace structural assessment or physical measurements. Record direction, position and date for photographs so different roof areas cannot be confused later.

Checkpoint · Dimensions reconcile; exclusion zones, delivery routes and maintenance access are mapped.
2

Record shading throughout the year

Identify potential shade from trees, neighbouring buildings, terrain and the array itself, accounting for seasonal changes and solar elevation. Record future extensions, tree growth and additional rooftop equipment as scenarios, rather than relying on one clear photograph at noon. Survey the orientation and available area of each roof slope separately.

Checkpoint · Measurements and photographs support the shading model; current and future conditions are distinguished.
3

Verify roof or ground capacity

Appropriately qualified specialists should assess roof structure, corrosion, profile, connections and remaining life. Ground-mounted projects require investigation of soil, groundwater, corrosion exposure and foundation construction conditions. Foundation selection and reinforcement must follow project calculations; a roof that looks sturdy is not sufficient evidence to approve installation.

Checkpoint · There are formal findings on load paths, weak areas and any additional testing required.
4

Investigate extreme weather and drainage

Gather local wind, snow, hail, flooding, salt, dust and high-temperature conditions. Check ponding, drainage paths and erosion on site. Risks may conflict: increasing module tilt can aid drainage but alter wind loading. Give designers the underlying evidence so they can evaluate these trade-offs together.

Checkpoint · Environmental design inputs have sources; flood levels and roof drainage have been checked.
5

Check electrical and communications access

Record the distribution single-line diagram, transformer and switchgear nameplates, proposed connection and metering points, cable routes and communications coverage. Cabinet inspections, live measurements and existing-protection checks belong to authorised electrical personnel. Clearly distinguish nameplate information, measurements and assumptions that still need verification.

Checkpoint · Electrical records are complete, assumptions are labelled and photographs identify the connection route.
6

Convert survey findings into design inputs

Classify findings as mandatory corrections, further tests or opportunities for optimisation, and assign responsibilities. Provide usable area, loading limits, foundation recommendations, shading inputs and construction logistics. Designers should acknowledge critical inputs; missing information must not silently become an assumption of no risk or no cost.

Checkpoint · The survey and design-input register agree, with deadlines for unresolved items.

Stage acceptance checklist

For learning and project preparation; not a replacement for formally signed acceptance. Checkmarks are saved only in this browser.

0 / 4 checked

View all records

Original technical sources

Sources provide general background or model-specific information. Foreign standards do not replace local requirements; obtain the latest manuals for the actual equipment before purchasing or construction.